What a data center deal should put in writing

Moonshots raised the idea of a grand bargain. Kansas shows how to turn it into questions about who pays, what residents receive, and who checks delivery.

By Singularity Farmer · Published

Share on X ↗
Capacity is what the project needs. Cost is who pays for it. Commitments are what the community can verify.

Start with the terms

A town can have the land and power to attract a data center and still leave the most important questions unanswered. Who pays for new capacity? What can residents count on receiving? Who checks that the company delivers?

On Moonshots #309, Alexander Wissner-Gross argued that communities with attractive sites should use their negotiating position to ask for public benefits. The point is worth taking seriously. A developer can price a clear obligation. Residents can evaluate it. Officials can put it in an agreement and check it after the vote. Moonshots #309 episode notes

Alexander Wissner-Gross discusses the “grand bargain” on Moonshots #309 · Watch on YouTube

Singularity Farmer wants more compute and more communities able to build around it. That starts with a proposal people can inspect. Our gross-versus-net framework asks what the host community keeps after accounting for what it supplies and what it takes on. Here’s how to turn that question into meeting preparation.

De Soto puts dates and triggers on the page

De Soto, Kansas, offers an example of what a public commitment can look like. The city says its council approved a second supplement to the Beale agreement on October 1, 2026, after the developer changed its cooling design and reduced its expected peak water demand. De Soto reports that the revised deal provides for roughly $9.4 million in developer-funded water infrastructure, including a new line under the Kansas River and an additional city well. City of De Soto agreement summary

The city also describes a Community Betterment Fund of up to $20 million. Its first $2 million is tied to Phase 1 building permits. Up to $18 million more depends on Phase 2 milestones. A council packet can show those as separate commitments, with columns for the trigger, the amount due, and the status. That lets residents distinguish an approved agreement from money collected. De Soto project documents and updates

De Soto City Council discussion of the Beale supplement · Watch on YouTube

The cooling change also shows why officials should ask for the design assumptions. A peak water estimate helps size infrastructure. An annual average helps compare total demand. Both need a defined project phase, water source, cooling design and operating conditions. If the design changes, the public should be able to see which costs and obligations change with it.

Put the power costs in separate rows

A large-load tariff can set obligations a city agreement does not control. In its approval of Evergy’s Kansas large-load plan, the Kansas Corporation Commission described minimum monthly billing based on 80% of contract demand, collateral and early-exit terms. It also distinguished upgrades needed solely to serve a new or expanding customer from transmission network upgrades, whose allocation follows a separate regional and federal process. Kansas Corporation Commission approval summary

A meeting packet should identify the party responsible for each kind of cost. Ask the utility to show dedicated facilities, shared transmission upgrades and the obligations that apply if the load arrives late or leaves early. Ask local staff to do the same for water, roads and emergency services. This makes it possible to see where each commitment belongs and who can change it.

Give every decision-maker something to prepare

Before a data-center meeting, identify the body taking action and the people who prepare its record. A planning committee may guide staff. A planning commission may recommend a zoning change. A city council or county commission may act on it. A utility regulator may decide a rate issue in a separate docket. The agenda and roster should tell readers which of those stages they are looking at.

Wichita’s project page, checked November 10, lists the Advance Plans Committee for November 12, the full planning commission’s consideration for December 3, and anticipated county consideration on December 16. It leaves the City Council date open. For the committee stage, Planning Director Scott Wadle and the planning department are the published route for written comments. The committee and full commission have separate rosters and roles. Wichita’s data-center timeline · Advance Plans Committee and public comments · Full planning commission roster and role

A preparation question for Wichita’s noise proposal is specific enough to put in the record. What would trigger an independent acoustic study, who would choose the qualified professional, and when could residents see the findings? The October 27 draft gives the zoning administrator discretion to require an independent study at the facility owner or operator’s expense when warranted. That proposed authority gives officials a concrete provision to discuss. October 27 draft regulations, printed page 21

Ask for these five things in the packet

  1. The decision. Name the body, agenda item, action sought and next step. Identify the members who will consider it and the staff member responsible for the report.
  2. The capacity. Show peak and average water demand separately, the power load by phase, and the assumptions behind each estimate.
  3. The bill. Assign each cost to a party and show which agreement, tariff or regulatory decision governs it.
  4. The benefit. Name the recipient, amount or deliverable, due date and event that triggers it. Ask what is already due and what depends on future phases.
  5. The follow-through. Name who verifies delivery, when the public can see the record, and what the agreement provides if the commitment is missed.

Bring one of those questions to the next meeting and ask where the answer will appear in the public record. A community that can put its terms in writing can make a clearer offer to developers and a clearer case to residents.

Keep building your understanding

More compute. More local upside.

Follow Singularity Farmer for practical notes on the power, water and community terms behind the buildout.

Source receipt

This article was prepared with AI assistance from the listed material, checked through the private Singularity Farmer newsroom, and explicitly approved for the website. Approval and publication are recorded separately.

  1. Moonshots #309 on Peter H. Diamandis’s YouTube channel ↗ · primary · checked
  2. Moonshots #309 publisher episode notes ↗ · first party · checked
  3. De Soto city summary of the Beale supplement ↗ · official · checked
  4. De Soto project documents and updates ↗ · official · checked
  5. De Soto City Council recording, October 1 ↗ · primary · checked
  6. Kansas Corporation Commission large-load rate plan approval summary ↗ · official · checked
  7. Wichita data center planning timeline ↗ · official · checked
  8. Advance Plans Committee roster and public comments ↗ · official · checked
  9. Full planning commission roster and role ↗ · official · checked
  10. Wichita-Sedgwick October 27 draft regulations ↗ · primary · checked
  11. Singularity Farmer gross-versus-net companion article ↗ · first party · checked