Data-center tracker · Project · Kansas
Beale Infrastructure data center campus (Mount Sunflower, LLC)
Beale Infrastructure (Mount Sunflower, LLC) · De Soto, Johnson County, KS
- Status
- under construction
- Developer
- Beale Infrastructure (Mount Sunflower, LLC)
- Location
- De Soto, Johnson County, KS
- Power (MW)
- Not reported
- Land (acres)
- 288 acresSite acresBasis: Mt Sunflower DA / Supplement #2 staff memo (NW corner Edgerton Rd & Energy Way)
- Investment
- $3.10BTotal (approx.)Basis: City of De Soto Beale page (~$3.1B, up to 4 buildings, phased to ~2035); minimum $700M investment within 7 years
- Water
- Source: City of De Soto
- Use: Closed-loop cooling (Supplement #2); peak day water demand reduced from 6.0 MGD to 300,000 gal/day (mostly fire-suppression fill); average daily much less; sewer demand reduced from 1.86 MGD to 50,000 gal/day
- Committed gallons per day: not disclosed
- Power utility
- Evergy (new public substation)
- Local signal
- Mixed
Upcoming
As of the record date. Confirm times with the host body before attending.
- Oct 1, 2026Council considers Supplement #2 to Mt Sunflower (Beale) Development Agreement: water/sewer demand cuts; $9.44M raw-water funding + $20M Community Betterment Fund; prior redacted utility terms unredacted · source ↗
- 2027Phase 1 completion target
Incentives
- IRB tax abatement + PILOT (development agreement approved Aug 2025): Up to 10-yr abatement per building; PILOT $0.411/sq ft escalating 1.5%/yr; resolution of intent for IRBs
- Electric franchise fee (approved): 3.75% (vs standard 5%), capped at $5.5M in year 1
Local organizing
- : Residents said they were 'blindsided' when building sizes grew
Notes
Flint Commerce Center, 103rd St & Edgerton Rd. City projects $300M+ in revenue over 25 years. Beale is also developer of Project Blue (Pima County, AZ). Supplement #2 (Oct 1 agenda Item 4a): closed-loop cooling cuts peak water from 6.0 MGD to 300k gal/day and sewer from 1.86 MGD to 50k gal/day; eliminates most previously contemplated $237M+ system upgrades; Beale contributions include $9.44M raw-water improvements and $20M Community Betterment Fund.
Timeline
- 2026Phase 1 (bldgs 1-2) site plan conditionally approved; grading underway
- Aug 2025Development agreement + IRB resolution of intent approved
Sources
- City of De Soto: Beale Data Center page ↗ · as of
- De Soto Oct 1 packet Item 4a Mt Sunflower Supplement 2 ↗ · as of
- De Soto Agenda Center Oct 1, 2026 ↗ · as of
Compiled from public records and reporting. Values a source did not state are marked “not reported”. Record ID ks-desoto-beale-mount-sunflower. Back to the tracker.