Data-center tracker · Project · Missouri
Nebius AI factory
Nebius · Independence, Jackson County, MO
- Status
- under construction
- Developer
- Nebius
- Location
- Independence, Jackson County, MO
- Power (MW)
- Initial: 800 MW
- Scalable to: 1,200 MW
- Land (acres)
- Not reported
- Investment
- $150BChapter 100 IRBBasis: Chapter 100 IRB authorization (not necessarily capex)
- Water
- Not reported
- Power utility
- Not reported
- Local signal
- Mixed
Upcoming
As of the record date. Confirm times with the host body before attending.
- Feb 2, 2027Special election primary for recalled seat
- Apr 6, 2027Special general election
Incentives
- Chapter 100 IRBs (approved March 2026): $150B; 90-98% abatement for 20 years
Timeline
- Sep 1, 2026Recall of Council member John Perkins passed (~68% yes); certified Sep 8
- May 2026Groundbreaking
- Mar 2026Council approved Chapter 100 IRBs
Sources
- KCTV5: Independence recall vote tied to Nebius data-center incentives ↗ · as of
- DCD: Nebius plans 800MW data-center campus outside Kansas City ↗ · as of
- City of Independence: Data Center and BESS Moratorium FAQs ↗ · as of
Compiled from public records and reporting. Values a source did not state are marked “not reported”. Record ID mo-independence-nebius. Back to the tracker.