Data-center tracker · Project · Wisconsin
GM/JATCO site data center (Viridian)
Viridian · Janesville, Rock County, WI
- Status
- cancelled
- Developer
- Viridian
- Location
- Janesville, Rock County, WI
- Power (MW)
- 800 MWProposed
- Land (acres)
- Not reported
- Investment
- $8BProposed
- Water
- Not reported
- Power utility
- Not reported
- Local signal
- Opposed
Upcoming
As of the record date. Confirm times with the host body before attending.
- Nov 3, 2026Voter-approval initiative for GM/JATCO site >$450M
Ballot measures
- Require Voter Approval for Development of GM/JATCO Site Exceeding $450 Million Initiative (Janesville, WI) · Election Nov 3, 2026 · on the ballot
Require voter approval before the city may lease, sell, transfer, or approve development of the undeveloped GM/JATCO site if the total project costs exceed $450 million
Local organizing
- No Janesville Data Center
Timeline
- Jun 2026Letter of intent expired; proposal dropped
Sources
Compiled from public records and reporting. Values a source did not state are marked “not reported”. Record ID wi-janesville-viridian-gm-jatco. Back to the tracker.