Data-center tracker · Project · Kansas

Project Jayhawk / Digital Astra Park North (Digital Realty)

Digital Realty (applicant entity: Digital Astra Park North, LLC) · De Soto, Johnson County, KS

Record updated · Sources checked on the dates listed below

Share on X ↗
Status
approved
Developer
Digital Realty (applicant entity: Digital Astra Park North, LLC)
Location
De Soto, Johnson County, KS
Power (MW)
Not reported
Land (acres)
  • TIF project area: 273.88 acres
  • Phase 1 site (approx.): 280 acres
  • Total land acquired (approx.): ~1,400-1,435 (per city/KC Star reporting)
Investment
$7.52BTotal development costBasis: Sunflower Redevelopment District TIF Project Plan 3 (feasibility study: $7,522.9M)
Water
  • Source: City of De Soto water (Kansas River alluvial aquifer); water and sanitary sewer served by De Soto
  • Use: City FAQ: outside-air cooling ~85-90% of the year, evaporative cooling at peak; ~1 MGD allocation referenced by city; cooling water not to be discharged to sanitary sewer; industrial wastewater treatment/reuse facility being explored
  • Committed gallons per day: not disclosed
Power utility
Evergy (Large Load Power Service tariff, >100 MW customers); one private substation plus one Evergy-operated substation ('Polaris') on site plan; Digital Realty says it will fund $300M+ transmission/substation work
Local signal
Mixed

Upcoming

As of the record date. Confirm times with the host body before attending.

  • 2026-10 (first week)Expected award of independent noise-consultant contract (final report ~April 2027) · source ↗
  • Oct 1, 2026, 6:30 PMJoint Planning Commission / City Council work session, City Hall (precedes 7:30 PM council; exact topic of joint session not separately posted) · source ↗
  • Oct 1, 2026, 7:30 PMCity Council regular meeting (moved from 7:00 PM). Agenda posted Sep 29: Call to Public; Item 4d Resolution 2104 scheduling Digital Realty TIF Project Plan 3 public hearing for Nov 19; Item 4e AA Land DEVCO IRB hearing (NOT Digital Realty); Item 4a Mt Sunflower/Beale Supplement #2 · source ↗
  • Oct 15, 2026, 7:00 PMCity Council regular meeting · source ↗
  • Oct 21, 2026, 6:00 PMComprehensive Plan public workshop, Senior Center Room, 32905 W. 84th St. · source ↗
  • Oct 27, 2026, 6:00 PMPlanning Commission regular meeting · source ↗
  • Oct 31, 2026, 10:00 AM'Hometown Table' informal conversation with council · source ↗
  • Nov 19, 2026City Council public hearing on Digital Realty TIF Project Plan 3 (Resolution 2104 schedules hearing; agenda item 4d on Oct 1 sets the date). Development agreement / project approval still separate and not yet scheduled. · source ↗
  • 2027-2030Construction start 2027, completion by 2030 (TIF plan)

Incentives

  • TIF (public hearing scheduled Nov 19, 2026 (Res. 2104 on Oct 1 agenda)): Sunflower Redevelopment District TIF Project Plan 3 (district est. by Ords. 2527/2540/2598); 20-year property-tax increment capture, 80% available for developer reimbursable costs, pay-as-you-go; est. TIF revenue ~$358,655,678; no sales-tax TIF
  • IRB / construction sales-tax exemption (possible): Developer may petition for IRB-based sales-tax exemption on construction materials if project does not qualify under recent state law
  • Development agreement (pending): Still to come before city council

Ballot measures

Local organizing

  • Neighbors United Coalition of De Soto, Kansas: Ban petition; concerns re noise, 41 diesel generators, transparency

Notes

Campus scaled back to ~1.5M sq ft (from ~3M sq ft/9 buildings) after a potential operator relationship 'didn't come to fruition' (Enrique Bellido, Digital Realty, KC Star Sep 27). Phase-1 building: 2 stories, 450,000 sq ft (225k/level), 61.5 ft, 30-ft louver screen, 189 parking spaces, 41 diesel backup generators, traffic signal at 103rd & Lexington. TIF plan: ~1,425,000 sq ft across two buildings. Jobs: 99 operating jobs and 500-600 construction workers phase 1 (KC Star); city page cites 250+ permanent/1,000+ peak construction. Data centers are permitted by right in M-1; city says it cannot ban them. City noise-code changes would apply to Digital Realty (no grandfathering). The Oct 1 IRB public hearing on De Soto's calendar is for AA Land DEVCO, LLC (commercial/multifamily, ≤$40M IRBs) — NOT Digital Realty. Oct 1, 2026 agenda (posted Sep 29): Item 4d schedules Digital Realty TIF Project Plan 3 public hearing for Nov 19, 2026 (Res. 2104). Item 4e IRB/tax-abatement hearing is for AA Land DEVCO, LLC (residential duplexes/6-plexes, ≤$40M IRBs, 75% abatement) — NOT Digital Realty. Joint PC/CC work session precedes council (council starts 7:30 PM).

Timeline

  • Sep 22, 2026Planning Commission approved phase-1 site plan 5-2 (Chad Martin, John Shultz no) and finding that TIF Plan 3 conforms with comprehensive plan (item 7C) · source ↗
  • Aug 2026TIF application announced at council meeting
  • Jul 23, 2026Community information session
  • Jun 4, 2026Project presented to De Soto City Council

Sources

  1. KC Star: De Soto planning commission approves Digital Realty data center site plan ↗ · as of
  2. KCBJ: Digital Realty Project Jayhawk / Evergy ↗ · as of
  3. KC Star: Kansas towns pursue data center bans ↗ · as of
  4. KC Star: Digital Realty TIF request ↗ · as of
  5. KC Star: De Soto noise study ↗ · as of
  6. KSHB: De Soto reviewing site application for second data center ↗ · as of
  7. City of De Soto: Digital Realty Data Center page ↗ · as of
  8. City of De Soto: Data Center Campus Project FAQ ↗ · as of
  9. De Soto Planning Commission 9/22/2026 packet (site plan staff report item 7b; TIF Plan 3 item 7c) ↗ · as of
  10. City of De Soto calendar: Joint PC/CC meeting Oct 1 ↗ · as of
  11. City of De Soto: Public Hearings & Notices ↗ · as of
  12. City of De Soto Agenda Center (Oct 1, 2026 agenda posted Sep 29) ↗ · as of
  13. De Soto Oct 1, 2026 City Council agenda cover ↗ · as of
  14. De Soto Oct 1, 2026 meeting materials (ccAGENDA; Item 4d Scheduling Public Hearing Re Digital Realty; Item 4e AA Land DEVCO IRBs) ↗ · as of
  15. City of De Soto calendar (Oct 2026 meetings) ↗ · as of

Compiled from public records and reporting. Values a source did not state are marked “not reported”. Record ID ks-desoto-digital-realty. Back to the tracker.