The learning desk · Source of truth

The US data-center tracker

Every data-center project, local ballot measure and policy we are following, with the numbers that matter locally: power, land, water, money and the next public meeting. Each record lists its sources and the date they were checked.

By Singularity Farmer · Records updated through · Refreshed every Wednesday

Singularity Farmer is pro-compute. We track opposition as closely as approvals, because communities negotiate better when they can see the whole field. Figures a source did not state are marked “not reported”, never estimated. Where a citation points to a news outlet’s front page, the article link is still being added. New to data centers? Start with the basics.

Projects

Kansas

ProjectLocationStatusPowerNext date
Beale Infrastructure data center campus (Mount Sunflower, LLC)
Beale Infrastructure (Mount Sunflower, LLC)
De Soto, Johnson County, KSunder constructionNot reportedOct 1, 2026
Council considers Supplement #2 to Mt Sunflower (Beale) Development Agreement: water/sewer demand cuts; $9.44M raw-water funding + $20M Community Betterment Fund; prior redacted utility terms unredacted
Compass Datacenters Topeka campus (Wakarusa area)
Compass Datacenters
Wakarusa area (unincorporated, south Topeka), Shawnee County, KSproposed400 MW2028-2031
Planned construction window
DAMAC Digital data center (Logistics Park Kansas City)
DAMAC Digital
Edgerton, Johnson County, KSapprovedNot reportedNone listed
El Dorado data center ban + Beltline Energy site due diligence
Beltline Energy LLC (NDA / site due diligence only; no formal proposal)
El Dorado, Butler County, KSNot reportedNot reportedNov 3, 2026
Election
Flint Hills Digital Campus
Kanza Park Place LLC (spokesman Garrett Nordstrom)
Emporia, Lyon County, KSproposedNot reportedNov 3, 2026
Election on high-impact data center ban
Prairie Horizon Data Campus
Beltline Energy
Emmett / St. Marys area, Pottawatomie County, KSproposed1,200 MWNone listed
Project Catalyst
Alcove Development + MDH Partners
Osawatomie, Miami County, KSproposed500 MWOct 14, 2026
Court hearing on petition lawsuit
Project Jayhawk / Digital Astra Park North (Digital Realty)
Digital Realty (applicant entity: Digital Astra Park North, LLC)
De Soto, Johnson County, KSapprovedNot reported2026-10 (first week)
Expected award of independent noise-consultant contract (final report ~April 2027)
Project LindaKansas City, Wyandotte County, KSproposed200 MWNone listed
Project Yardbird (Quindaro plant site)
PowerTransitions
Kansas City, Wyandotte County, KSproposed200 MWNone listed
Proximity Park data center + natural gas plant (Lightfield Energy)
Lightfield Energy LLC
Ottawa, Franklin County, KScancelledNot reportedOct 20, 2026
Court hearing on validity of ban initiative
Red Wolf data center campus (Kansas Speedway area)
Red Wolf DCD Properties
Kansas City, Wyandotte County, KSpaused600 MWNone listed
Spring Hill data center (191st & Renner)
Bullock Capital / Colossus Advisors
Spring Hill, Johnson County, KScancelledNot reportedNone listed

Arizona

ProjectLocationStatusPowerNext date
Project Blue
Beale Infrastructure
Tucson area (unincorporated), Pima County, AZunder construction286 MWNone listed

Colorado

ProjectLocationStatusPowerNext date
GlobalAI data center (Weld County / Windsor area)
GlobalAI Cloud Inc. (per BizWest tags)
Windsor area, Weld County, COapprovedNot reportedSep 29, 2026
Citizens group collecting signatures for referendum on the approved facility plus initiative requiring voter approval for future DC development/expansion
Northeast Brighton data center campus (15518 WCR 4)Brighton, Adams/Weld County, COproposedNot reportedNone listed

Florida

ProjectLocationStatusPowerNext date
Project Tango + Palm Beach County hyperscale moratoriumPalm Beach County, FLcancelledNot reportedNone listed

Georgia

ProjectLocationStatusPowerNext date
Project Camellia (OpenAI)
OpenAI (developer entity Octans GA LLC)
near Rincon (Savannah Gateway Industrial Hub), Effingham County, GAapproved3,210 MW2028-2032
Construction window

Kentucky

ProjectLocationStatusPowerNext date
Mercer County data center zoning (near Shaker Village / coal plant)Mercer County, KYproposedNot reportedNone listed

Michigan

ProjectLocationStatusPowerNext date
'The Barn' (Stargate) campus
Related Digital (OpenAI/Oracle Stargate)
Saline Township, Washtenaw County, MIunder construction1,400 MWOct 23, 2026
EGLE wastewater permit public comment deadline
Augusta Township data center rezoning
Thor Equities
Augusta Township, Washtenaw County, MIcancelledNot reportedNone listed

Missouri

ProjectLocationStatusPowerNext date
Downtown KC 20-story data center (304 W 10th St)
Revitalization Unlimited
Kansas City, Jackson County, MOproposed30 MWNone listed
Festus data center
CRG
Festus, Jefferson County, MOpausedNot reportedNone listed
Google Kansas City data center (Hunt Midwest Business Center) + Project Mica
Google
Kansas City (Northland), Clay County, MOunder constructionNot reportedNone listed
Meramec Valley Tech Park
BLE Landholdings / Beltline (reported)
Pacific, Franklin/St. Louis County, MOproposedNot reportedNone listed
Nebius AI factory
Nebius
Independence, Jackson County, MOunder construction800 MWFeb 2, 2027
Special election primary for recalled seat
Peculiar data center
Diode Ventures
Peculiar, Cass County, MOcancelledNot reportedNone listed

Nebraska

ProjectLocationStatusPowerNext date
Project HorizonKearney, Buffalo County, NEapproved368 MWNone listed

Nevada

ProjectLocationStatusPowerNext date
Eldorado Valley data centers (Question 1) / TS2
Townsite Solar 2 LLC (TS2 proposal, separate)
Boulder City, Clark County, NVproposed167 MWNov 3, 2026
Election

New Hampshire

ProjectLocationStatusPowerNext date
Merrimack Station data center viability study
Granite Shore Power
Bow, Merrimack County, NHproposed350 MWNone listed

Ohio

ProjectLocationStatusPowerNext date
EdgeConneX Ashville campus + PowerConneX gas plant
EdgeConneX / PowerConneX
Ashville, Pickaway County, OHproposed800 MWNov 3, 2026
Referendum on Resolution 06-2026
Wilmington data center campus
Ardent / TAC (reported)
Wilmington, Clinton County, OHapprovedNot reportedNov 3, 2026
4 rezoning referendums

Oklahoma

ProjectLocationStatusPowerNext date
Aligned Data Centers campus near Amber
Aligned Data Centers ((OK) Propco LLC)
near Amber (unincorporated), Grady County, OKproposedNot reportedOct 6, 2026
Aligned public meeting, Amber-Pocasset High School

Pennsylvania

ProjectLocationStatusPowerNext date
Former Alcoa site hyperscale campus
TECfusions
Upper Burrell Township, Westmoreland County, PApausedNot reportedNone listed
PAX-1 data center complexMiddlesex Township, Cumberland County, PAunder constructionNot reportedNone listed

Wisconsin

ProjectLocationStatusPowerNext date
GM/JATCO site data center (Viridian)
Viridian
Janesville, Rock County, WIcancelled800 MWNov 3, 2026
Voter-approval initiative for GM/JATCO site >$450M
Lighthouse campus (Vantage; OpenAI/Oracle)
Vantage Data Centers
Port Washington, Ozaukee County, WIunder construction902 MW2027 (late)
First handovers
Midtown Milwaukee data center + citywide moratoriumMilwaukee, Milwaukee County, WIcancelledNot reportedNone listed
Wrightstown data center (Cloverleaf)
Cloverleaf Infrastructure
Wrightstown, Brown/Outagamie County, WINot reportedNot reportedNone listed

Ballot measures

Local measures on data centers that are not yet tied to a single project record. Measures attached to a project appear on that project’s page.

MeasureLocationLocal signalNext date
Alhambra (CA): Measure DBAlhambra, CAOpposedNone listed
Monterey Park (CA): Measure NDCMonterey Park, CAOpposedNone listed
Edgewater (FL): Prohibit New Data Centers AmendmentEdgewater, FLOpposedNone listed
Bloomington (IL): Data Center Moratorium Advisory MeasureBloomington, ILOpposedNone listed
Chouteau (Madison County) (IL): Permit Data Centers Advisory MeasureChouteau, Madison County, ILSupportiveNone listed
Granite City (Madison County) (IL): Permit Data Centers Advisory MeasureGranite City, Madison County, ILSupportiveNone listed
Joliet (Will County) (IL): Construction of AI Data Centers Advisory QuestionJoliet, Will County, ILSupportiveNone listed
Morgan (IL): Data Center Construction and Operation Advisory MeasureMorgan, ILOpposedNone listed
Nameoki (Madison County) (IL): Permit Data Centers Advisory MeasureNameoki, Madison County, ILSupportiveNone listed
Venice (Madison County) (IL): Permit Data Centers Advisory MeasureVenice, Madison County, ILSupportiveNone listed
Butte-Silver Bow voter-approval initiative (off ballot)Butte-Silver Bow, MTOpposedNone listed
Conneaut (OH): Issue 10Conneaut, OHOpposedNone listed
Defiance (OH): Prohibit Data Center Construction InitiativeDefiance, OHOpposedNone listed
Granville (OH): Prohibit Data Center Construction InitiativeGranville, OHOpposedNone listed
Grove City (OH): Issue 28Grove City, OHOpposedNone listed
Hubbard (OH): Prohibit Data Centers InitiativeHubbard, OHOpposedNone listed
Monroe (Adams County) (OH): Zoning Regulations InitiativeMonroe, Adams County, OHMixedNone listed
Monroeville (OH): Allow Data Center Development Advisory MeasureMonroeville, OHSupportiveNone listed
Oregon (OH): Prohibit Data Center Construction Over 25 Megawatts InitiativeOregon, OHOpposedNone listed
Pataskala (OH): Prohibit Data Centers InitiativePataskala, OHOpposedNone listed
Perry (OH): Issue 16Perry, OHOpposedNone listed
Piqua (OH): Prohibit Data Center Construction InitiativePiqua, OHOpposedNone listed
Sprigg (Adams County) (OH): Zoning Regulations InitiativeSprigg, Adams County, OHMixedNone listed
Sunbury (OH): Prohibit Construction of Data Centers InitiativeSunbury, OHOpposedNone listed
Trenton (OH): Issue 17Trenton, OHOpposedNone listed
Upper Sandusky (OH): Data Center Construction Prohibition Charter AmendmentUpper Sandusky, OHOpposedNone listed
Urbana (OH): Prohibit Construction of Data Centers InitiativeUrbana, OHOpposedNone listed

Local policies

Jurisdiction-wide actions such as moratoriums and zoning changes.

PolicyLocationLatest action
Los Angeles County temporary ban on large-scale data centers (unincorporated)Los Angeles County, CASep 2026
County temporarily prohibited large-scale data centers in unincorporated areas while pursuing permanent zoning changes (exact ordinance date not verified in primary source this run)
Mesa County 1-year data center moratoriumMesa County, COSep 29, 2026
Commissioners approved 12-month moratorium on acceptance/processing/approval of land-use applications for data centers in unincorporated Mesa County; effective immediately; no projects currently in works
Thornton 1-year data center moratoriumThornton, Adams County, COSep 2026
City Council approved ~1-year moratorium on new data centers larger than ~50,000 sq ft (exact date ~Sep 8–9 per social posts; primary ordinance link not captured this run)
Marion County data center moratoriumMarion County, FLSep 15, 2026
12-month moratorium passed 4-1
Frederick County referendum + moratoriumFrederick County, MDJun 30, 2026
MD Supreme Court blocked referendum
Charlotte proposed 11-month data center moratorium extensionCharlotte, Mecklenburg County, NCSep 29, 2026
City Council unanimously set public hearing on proposed 11-month extension
Davidson County proposed 4-month data center moratoriumDavidson County, NCSep 29, 2026
Board of Commissioners voted 4-2 to schedule public hearing on proposed 4-month moratorium (shorter than previously discussed 6-month)
Cleveland 3-month data center permit freeze + hearingsCleveland, Cuyahoga County, OHSep 29, 2026
Second public hearing, Cleveland City Hall 5–8 PM ET
Lubbock 90-day moratorium processLubbock, Lubbock County, TXSep 22, 2026
Council voted 5-2 to begin 90-day moratorium process (2 hearings required); 18-month pause petition got no second
Texas state data center permit review pause (Abbott)TXSep 2026
Gov. Abbott ordered state environmental regulators to pause review of data center permits for added grid/water scrutiny; expands earlier pause to projects with own power (exact order date not verified in primary source this run)
Prince William County ends by-right data centersPrince William County, VASep 22, 2026
Board voted unanimously to end by-right data center development; 90-day grace period